Work on John Compton Dam Rehabilitation Project phase two set for June

By WASCO

 Share This On:

(PRESS RELEASE) — Work on the second phase of the John Compton Dam Rehabilitation Project (JCD02) — dredging of the reservoir and transport of sediment — is set to begin in June 2019.

The announcement was made by WASCO’s representatives, as well as the contractor for JCD02, VINCI Construction Maritime et Fluvial, who met with residents of Tete Chemin Millet, Vanard, Jacmel and environs during a town-hall-style meeting at the Millet Infant School on Sunday, April 14, 2019.


The meeting was necessary to alert residents about the hauling of heavy equipment which will be transported through their communities in preparation for the JCD rehabilitation works.

Project Manager for JCD02, David Ferrao of VINCI Construction Maritime et Fluvial, disclosed that the suction dredge, which will be used to de-silt the John Compton Dam, is already en route to St Lucia from Europe and is expected to arrive at Port Castries by April 30, 2019.


Once the equipment arrives on island, a total of 14 trailer trucks will be used over a five-day period to transport the heavy dredging equipment from Port Castries to the John Compton Dam.

Assembling of the marine equipment will then take place.

Specialized experts, including three divers, have been contracted to conduct the under-water works. The crew will be responsible for the removal of woody debris from the reservoir, among other responsibilities. Permanent onshore pipelines will also be laid from the reservoir to the sediment disposal area in preparation for the suction dredging.


Meanwhile, Head of the Project Management Unit of WASCO, Mr Gordon Wyke, presented a status report on phase one of the project, JCD01 – construction of the sediment disposal area (SDA). The works are being undertaken by Mega Contracting Inc., a local construction company.

JCD01 began in May 2018 but the works have been hindered due to heavy rains, specifically during the last quarter of 2018. Once completed, the SDA will be used to dispose of the sediment from the reservoir when the dredging phase begins in June. Therefore, preparations are well advanced for the commencement of phase two of the project.

Hence, WASCO is requesting the co-operation of all residents and commuters in the area to ensure that the traffic management plan is implemented to cause minimum inconvenience.

(0)(0)
This article was posted in its entirety as received by stlucianewsonline.com. This media house does not correct any spelling or grammatical error within press releases and commentaries. The views expressed therein are not necessarily those of stlucianewsonline.com, its sponsors or advertisers.

One comment

  1. Is anybody in a position to advise why the community of Jacmel was involved in the town hall meeting. I accept that Jacmel residents would be impacted by heavy equipment moving on the road from the distillery to Morne D'or and towards Vanard but is that the extent of it or is some of the silt garbage destined for the Jacmel area itself?

    (0)(0)

Leave a Reply

Your email address will not be published.

This site uses Akismet to reduce spam. Learn how your comment data is processed.